Adams Project – 13 Unit Multifamily Electrification

Project Type

Multifamily capital replacement, building envelope and systems upgrade

Scope of Work

  • Removal of legacy Envi heaters

  • Installation of ductless heat pump systems across all units

  • Installation of heat pump water heaters

  • Subfloor insulation improvements

  • Air sealing performed in accordance with current energy code requirements

Execution and Constraints

  • Occupied multifamily building

  • Coordinated sequencing of mechanical, insulation, and air sealing scopes

  • Code driven air sealing verified during execution

Schedule and Delivery

  • Total project duration, approximately 1.5 weeks

Outcome

  • Electrified space heating and domestic hot water systems

  • Improved thermal performance of the building envelope

  • Increased occupant comfort and reduced energy demand