Adams Project – 13 Unit Multifamily Electrification
Project Type
Multifamily capital replacement, building envelope and systems upgrade
Scope of Work
- Removal of legacy Envi heaters
- Installation of ductless heat pump systems across all units
- Installation of heat pump water heaters
- Subfloor insulation improvements
- Air sealing performed in accordance with current energy code requirements
Execution and Constraints
- Occupied multifamily building
- Coordinated sequencing of mechanical, insulation, and air sealing scopes
- Code driven air sealing verified during execution
Schedule and Delivery
- Total project duration, approximately 1.5 weeks
Outcome
- Electrified space heating and domestic hot water systems
- Improved thermal performance of the building envelope
- Increased occupant comfort and reduced energy demand